Tenant Improvement Work

Construction at SL Green Realty Corp. is a simple structured process. Each step is accompanied with a letter clearly outlining the next steps, as well as the construction guidelines that your firm must follow.

The process is as follows:
  1. The tenant submits drawings for review to the following parties:
    • Property Manager: Eugene Lee
    • Chief Engineer: Roland Hontoria
    • Vice President of Construction: Peter Flynt
    • Reviewing Engineers for Comments:
      • MGJ Associates (MEP)
      • Severud Associates (Structural)
      • Moed de Armas & Shannon (Redevelopment Architect)
      • Robert Director Associates (Redevelopment Engineer)
  2. The Construction Department issues Letter 1, which outlines additional materials required:
    • Additional drawings (Architectural, Structural, HVAC, Electrical, Plumbing, Sprinkler, Fire Alarm)
    • General Contractors Insurance & Indemnification Agreement
    • Permit Expeditor assigned by SL Green to property: Rizzo Group
      • The expeditor assigned by SL Green MUST be used unless stipulated otherwise in the lease.
  3. Permit applications submitted by the building assigned expeditor for VP signature
  4. The reviewing engineer(s) & PM submit comments to CA/VP. The comments are reviewed and Letter 2 is sent with said comments attached. Letter 2 must be signed and returned by the tenants.
  5. The tenant must resubmit drawings, conforming to the Reviewing Engineer's & PM's comments, to PM, CE, & CA/VP. If all comments are addressed and CA & PM have copies of Contractors Insurance & Indemnification Agreement as well as the appropriate permits, Letter 3 is issued, granting final approval. All subsequent coordination, scheduling, access, etc. must be arranged through the Property Manager.
  6. Project begins; SLG inspects construction site periodically.
Note: For additional information please refer directly to your lease.